掘辅运配巷缩小工作面绕过陷落柱NPT技术优化
NPT Technology Optimization of Mining through Collapse Column by Driving Auxiliary-transportation Roadway
-
摘要: 为研究工作面安全高效绕过陷落柱技术,依据平朔井工一矿实际生产情况,采用掘辅运配巷缩小工作面绕过陷落柱,分析了绕过陷落柱期间的主要工序及其衔接关系,利用NPT技术对绕过陷落柱工序安排进行优化,确定了总工期与关键路线;并计算确定了各工序合理的开始与结束时间,从而实现高产高效安全生产。Abstract: In order to safely mining through collapse column in Pingshuo Underground 1st Mine,applying auxiliary-transportation roadway to shortening mining face. This paper analyzed main working processes and cohesion relationship when mining through collapse column. Working process was optimized by NPT technology. Construction time and key path was determined,rational start and end time of every process was calculated. High production and high efficiency was realized.